- Completion Certificate
- Cutting / Trimming of Trees
- Demarcation of the Plot
- Demolition of HouseBuilding
- Duplicate Site Plan or Completion Certificate
- Implementation of Burial Procedure
- Installation of Generator in Commercial Building
- Issuance of Burial Certificate
- New Water and Sewerage Connection
- No Demand Certificate
- Open Plot for Stacking of Construction Material
- Permission for use of Mechanical Excavator
- Refund of Security
- Registration of the Architect
- Renovation Repair of House Building
- Site Plan Issuance
- Submission of Building Drawings Plans
- Temporary Sewerage Connection
- Use of Adjacent Plot as Lawn
Demarcation of the Plot
Demarcation of the plot is required before construction. This procedure takes place after the approval of Building Plans.
Service | Timeline | Charges | Delivery |
Demarcation |
Phase 1-4 4 working days Phase 5,6 & 8 7 working days |
Nil | Building Control Branch |
Documents Required
- Demarcation Form duly completed by the owner or holder of Special Power of Attorney approved by DHA.
- Copy of TIP Tax paid to Cantt Board.
- Undertaking on Rs. 50/- Stamp Paper for the use of water pump during the construction period.
- No Objection Certificate for construction (issued by Finance Branch).
Procedure
- Demarcation Forms are available at Customer Care Services, DHA Office.
- Complete set of documents and Demarcation Forms duly signed will be submitted to Customer Services Officer Building Control Branch.
- Client will be given an acknowledgment and date to obtain Demarcation Papers.
Note: Demarcation is valid for one month only in case construction activity has not commenced.
Demolition of House/Building
Service | Timeline | Charges | Delivery |
Permission for Demolition of House/Building | 12 Working Days | Rs 25000/- Refundable Security | Permission letter will be dispatched at applicant’s address. |
Documents Required
- Application from Owner / Attorney to Director Building Control.
- Copy of Computerized National Identity Card of Owner.
- Copy of Completion Certificate of particular house / building.
Procedure
- The required documents will be submitted to the Customer Care Services.
- DHA field staff will visit the site.
- A letter will be dispatched along-with payment challan on account of Security Charges and specimen of undertaking for demolition of house / building to the Director Building Control.
- Copy of paid challan and undertaking on Rs. 50/- Stamp Paper will be submitted at the Customer Services Centre.
- Permission letter for Demolition of House/Building will be dispatched to the owner after verification of documents and inspection of house / building at site.
Duplicate Site Plan or Completion Certificate
Service | Timeline | Charges | Delivery |
Duplicate Site Plan or Duplicate Completion Certificate | 12 working days |
Duplicate Site Plan charges @ Rs. 1000/- Duplicate House Completion Charges @ Rs. 1000/- |
Building Control Branch |
Documents Required
- Application addressed to Director Building Control requesting for the issuance of Duplicate Site Plan or Completion Certificate.
- 1 x photocopy of Computerized National Identity Card.
- 1 x photocopy of paid challan for the duplicate Site Plan charges or duplicate Completion Certificate @ Rs. 1000/-.
Procedure
- Application along-with above documents will be submitted to Building Control Branch, DHA office, through Customer Care Services.
- Customer Services Officer will issue an acknowledgment against the documents.
- Duplicate Site Plan or Completion Certificate will be issued to Owner / Attorney from Building Control Branch.
Implementation of Burial Procedure
Service | Timeline | Charges | Delivery |
Following Services will be Provided by DHA Lahore: Ambulance |
Minimum 4-6 hours notice required | Free of cost | Burial of deceased in DHA Graveyard |
Documents Required
- Copy of Computerized National Identity Card of owner and deceased.
- Copy of Allotment / Transfer Letter of owner.
- Proof of relationship with owner of plot / house / building.
Procedure
- The required documents should be submitted at the DHA Complaint Centre, located under Overhead Water Tank, Sector A, Phase-I.
- DHA Security Staff will verify the death and Building Control Branch will confirm the eligibility of deceased for burial in DHA Graveyard.
- Ambulance and necessities of ghusal as mentioned above will be provided by DHA Lahore.
- Spouse of deceased or any representative will coordinate with Complaint Receiver, Supervisor Building Control and DHA Graveyard Staff for preparation of Grave and time of burial.
- Ambulance will be provided for transportation of dead body to DHA Graveyard.
- Burial / Maintenance of the grave
Installation of Generator in Commercial Building
Service | Timeline | Charges | Delivery |
Installation of generator in commercial building | 08 Working Days | Free of cost | Permission letter will be dispatched to the customer’s address. |
Documents Required
- Application from Owner / Attorney.
- Copy of Computerized National Identity Card of Owner.
- Copy of Allotment / Transfer Letter.
- Affidavit / No Objection Certificate from Owner / Tenant.
Procedure
- The required documents should be submitted at the Customer Care Services by the applicant.
- Permission will be granted and approval letter will be dispatched to Owner / Tenant after site verification.
Issuance of Burial Certificate
Service | Timeline | Charges | Delivery |
Issuance of Burial Certificate | 03 Working Days | Free of cost | Building Control Branch. |
Documents Required
- Application from Spouse/Representative. Download
- Copy of Computerized National Identity Card of Owner / Deceased.
- Copy of Allotment/Transfer letter.
Procedure
- The required documents should be submitted at the Customer Care Services (Building Control Section) by the applicant.
- Burial Certificate will be received from Building Control Branch, DHA office.
New Water and Sewerage Connection
Service | Timeline | Charges | Delivery |
New Water & Sewerage Connection | Subject to finishing of construction activities without construction violations |
Water Connection Fee @ Rs. 7000/- Sewerage Connection Fee @ Rs.4000/- |
Water and Sewerage connections will be provided through main pipes on site |
Documents Required
- Opening of Water & Sewerage Connections Form duly filled by the Owner / Attorney.
- 1 x Photocopy of Water Connection Charges (paid challan).
- 1 x Photocopy of Sewerage Connection Charges (paid challan).
- 1 x photocopy of Computerized National Identity Card of owner.
Procedure
- Water & Sewerage Connection Forms are available at the Reception of Customer Care Services DHA office free of cost (Download).
- After collecting the Water & Sewerage Form client has to visit Customer Services Officer (Building Control Branch) for the preparation of Water & Sewerage Connection Charges.
- The client will pay the dues as per Payment Challan in the designated bank.
- Acknowledgment will be issued by Customer Care Services (Representative Building Control Branch).
- Water & Sewerage Connections will be provided after flooring, plastering, gate, doors, windows, electrification and plumbing of the house / building are ready.
- After site visit by the field staff of Building Control Branch and if satisfied with the construction as per approved drawing, having no construction violations, recommendation for opening of both the connections is made.
- After provision of Water Connection, previously installed water pump by the owner for construction activities will be removed according to DHA Construction Byelaws.
- Sewerage Connection will be completely opened for the proper out flow after completion of above.
No Demand Certificate
Service | Timeline | Charges | Delivery |
Issuance of No Demand Certificate | 4-6 Working Days (as per Site & Phase requirement) |
Security Charges & Non construction penalty (If applicable) Any other charges as intimated by Finance Branch |
Client will be informed by Building Control Branch in case of construction violation in house / building. Client will coordinate with Transfer & Record Branch and Finance Branch for payment of dues and date of transfer. |
Documents Required
- Copy of Site Plan issued by Building Control Branch in name of present owner.
- Copy of Completion Certificate (in case of house / building).
- Copy of Allotment / Transfer Letter.
- Copy of Computerized National Identity Card of owner.
- No Objection Certificate from Cantt Board (relating to TIP Tax).
- No Objection Certificate from W&R Directorate, GHQ Rawalpindi in case of service benefit plots / plots allotted out of defence quota from GHQ AG’s Branch.
Procedure
- Client will submit No Demand Certificate Form along-with required documents to Customer Services Officer (Transfer & Record Branch). (Download Specimen)
- DHA field staff will visit the site in case of constructed house/building for ground verification.
- If construction violations are observed, owner will be informed on corresponding address or in case of no violation No Demand Certificate will be processed to Transfer & Records Branch through Finance Branch for clearance of dues and transfer of plot.
- The client can check the status and collect the Payment Challan from Finance Branch, DHA office.
Use of Open Plot for Stacking of Construction Material / Temporary Hut
Service | Timeline | Charges | Delivery |
Use of open plot for stacking of construction material | 08 Working Days | Free of cost | Permission letter will be dispatched at applicant’s address. |
Documents Required
- Application from Owner / Attorney.
- Copy of Computerized National Identity Card of Owner.
Procedure
- The required documents should be submitted at the Customer Care Services.
- DHA field staff will visit the site.
- A letter will be dispatched to the applicant along-with specimen of undertaking for use of open plot for stacking of construction material and construction of temporary hut.
- Undertaking on Rs. 50/- Stamp Paper will be submitted at Customer Care Services by the applicant.
- Permission letter for use of open plot will be sent to the Owner / Attorney.
Permission for use of Mechanical Excavator
Service | Timeline | Charges | Delivery |
Permission for use of Mechanical Excavator | 12 Working Days | Rs 25000/- Refundable Security | Permission letter will be dispatched to the customer’s address. |
Documents Required
- Application from Owner to Director Building Control.
- Copy of Computerized National Identity Card of Owner.
Procedure
- The required documents will be submitted to the Customer Care Services.
- DHA field staff will visit the site.
- A letter will be dispatched to the applicant along with payment challan on account of security charges and specimen of undertaking for use of mechanical excavator.
- Copy of paid challan and undertaking on Rs 50/- Stamp Paper will be submitted at the Customer Care Services.
- Permission letter for use of excavator will be dispatched to the Owner’s address.
Refund of Security
Service | Timeline | Charges | Delivery |
Refund of Security | 1 Month | Free of Cost | Finance Branch |
Documents Required
- Application from Owner / Attorney to Director Building Control.
- Copy of Computerized National Identity Card of Owner.
- Original Paid Challan.
Procedure
- The required documents will be submitted at Customer Care Services.
- DHA Management approves the refund of security to owner.
- A letter for collection of cheque from Finance Branch will be dispatched to the owner.
Registration of the Architect
Service | Timeline | Charges | Delivery |
Registration of Architect | 30 working days | Bank Draft of Rs. 5000/- | Approval letter will be dispatched to applicant’s address |
Documents Required
- Copy of Bachelors Architect Degree.
- Registration with Pakistan Council of Arts & Town Planners (PCATP).
- Copy of Computerized National Identity Card of the Principal Architect.
- List of Architect team with bio-data of each individual and certified copies of their certificates / degrees.
- Registration with other departments / authorities.
- Company Profile.
- Three specimen signatures on letter head paper with stamp of Principal Architect.
- Pay order / Bank Draft for Rs.5,000 (Rupees five thousand only) in the name of DHA Lahore, as processing Fee.
- Affiliation Certificate of MSc / PhD Structural Engineer with a copy of his / her degree.
- Copy of National Tax Number certificate.
Procedure
- Submit the required documents with the Company Profile for its approval at Customer Care Services, DHA office.
- Customer Services Officer will give an acknowledgment for the submission of documents.
- After verification of documents and visiting Architect’s office recommendation will be made for registration with DHA Lahore.
- Principal Architect will be called for an interview with DHA Management for approval.
Renovation / Repair of House / Building
Service | Timeline | Charges | Delivery |
Renovation/Repair of House/Building | 12 Working Days |
5 Marla @ Rs.1000 10 Marla @ Rs.1500 1 Kanal @ Rs.3000 2 Kanal @ Rs.4000 Commercial – Upto 8 Marla – @ Rs.2000 Commercial – > 8 Marla – @ Rs.4000 |
Permission letter will be dispatched at the customer’s address. |
Documents Required
- Written application with details of intended Renovation / Repair works of house / building.
- Copy of Computerized National Identity Card of the owner / attorney.
- Copy of Allotment / Transfer Letter.
Procedure
- The required documents will be submitted at the Customer Care Services.
- DHA field staff will visit the site.
- A letter will be dispatched by Building Control Branch to the applicant along-with payment challan on account of debris charges and specimen of undertaking for Renovation / Repair of house / building.
- Copy of paid challan and undertaking on Rs. 50/- Stamp Paper will be submitted at Customer Care Services (Building Control Section).
- Letter of approval will be dispatched to the owner to commence the Renovation/Repair of house / building.
Site Plan Issuance
Site plan is a certificate that indicates area and the dimensions of the plot, duly issued by DHA Lahore office.
Service | Timeline | Charges | Delivery |
Site Plan Issuance | 8 working days | Site Plan Charges Rs. 1700/- | Building Control Branch |
Documents Required
- 2 x Site Plan Application Forms.
- 1 x Photocopy of Allotment / Transfer Letter.
- 1 x Photocopy of Computerized National Identity Card of Client.
Procedure
- Site Plan Application Forms are available at Customer Care Services of DHA Office free of cost (Download Siteplan)
- Site Plan Application Forms along-with required documents will be submitted at Customer Care Services.
- A computer number and date for the collection of dues will be given on computer generated receipt to the client.
- Challan Form for dues (if any) will be issued from Finance Branch after five working days.
- Site Plan can be received from Customer Care Centre Counter No. 11, after 2 working days of payment of dues.
Submission of Building Drawings / Plans
Service | Timeline | Charges | Delivery |
Submission of Building Drawings/Plans | – |
Drawing Scrutiny Fee @ Rs.2/-Sq ft of total covered area DHA Construction Bylaws Book @ Rs. 110/- per book Debris charges 5,7&10 Marla @ Rs. 4200/- 1 Kanal @ Rs. 5300/- 2 kanal & above @ Rs. 6300/-Commercial @ Rs. 6300/- |
Letter of approval will be dispatched to customer’s address |
Documents Required
- Architect Stability Certificate (1 x original and 1 x photocopy).
- Form A & B of Cantt Board.
- 1 x Tracing Cloth, 7 x Ammonia Prints, 2 x Ammonia Prints of Fire Fighting Plan (only for commercial) and 1 x soft copy of Building Drawings/Plans in form of CD (AutoCAD format).
- Copy of Allotment / Transfer Letter.
- Copy of Site Plan issued by Building Control Branch in current owner’s name.
- Copy of Computerized National Identity Card of the owner.
- Copy of paid challan for the Drawing Scrutiny Fee.
- General undertaking on Stamp Paper Rs.50.00 (specimen available with Drawing Section).
- Undertaking on Stamp Paper Rs.50.00 for Temporary Lavatory in Residential Buildings (specimen available with Drawing Section).
- Undertaking on Stamp Paper Rs.50.00 in case of Basement (specimen available with Drawing Section).
- Undertaking on Stamp Paper Rs.50.00 for Swimming Pool for Residential Building. (specimen available with Drawing Section).
- Undertaking for No Claim of Services on Stamp Paper Rs.50.00 for Ph-VI.
- Structure Stability Certificate from PhD / MSc Structural Engineer (for commercial only).
Note: All undertakings to be duly signed by owner and attested by the Oath Commissioner.
Procedure
- The Building drawing plan documents will be submitted to Customer Care Counter Nos. 6,7,8 & 9 for detailed checking.
- Customer Care Counter No. 11 will issue payment slip for generation of challan by Finance Branch.
- The Customer Services Officer will issue payment challan according to the payment slip which will be paid in branches of banks mentioned on reverse of challan.
- A photocopy of paid challan will be attached with the Building Drawings / Plans along-with documents tagged in a file.
- Acknowledgment Slip will be issued to client for the submission of Building Drawings/Plans.
- After receiving the approval letter of drawing, member will visit Building Control Branch and get the Payment Slip for TIP Tax. Thereafter client will get the Payment Challan from Finance Branch for deposit in National Bank of Pakistan (NBP).
- Owner will provide 3 x Copies of Paid Challan to Building Control Branch and collect the Building Drawing / Plan.
Note: After approval of Building Drawing / Plan, member will obtain demarcation from DHA Lahore, after which construction should commence within one month and completion of building within two years.
Requirements for Submission of Drawing
Architect Stability Certificate
Temporary Sewerage Connection
Service | Timeline | Charges | Delivery |
Temporary Sewerage Connection | 12 Working Days | Free of cost | Temporary sewerage connectivity on site |
Documents Required
An application from owner, to Director Building Control, requesting for the opening of temporary sewerage connection. (Download Specimen)
Procedure
- Client can start the construction work after receiving demarcation papers and is bound to construct Septic Tank as per approved drawing and Temporary Lavatory within the plot area.
- The application for Temporary Sewerage Connection will be submitted to Customer Services Officer (Building Control Branch).
- Septic Tank & Temporary Lavatory (connected with each other) should be ready before the field staff visit within 10-12 working days.
- Temporary Sewerage Connection will be provided to particular house / building when Temporary Lavatory has been constructed and connected with Septic Tank.
Use of Adjacent Plot as Lawn
Service | Timeline | Charges | Delivery |
Use of Adjacent Plot as Lawn | 12 Working Days | Free of cost | Permission letter will be dispatched at the customer’s address. |
There should be one owner of the plot and adjacent house or the owners should be relatives (Parents, Children, Husband/ Wife).
Documents Required
- Site Plan of House and Adjacent Plot.
- Copy of Allotment/Transfer letters of House and Adjacent Plot.
- Copy of Computerized National Identity Card of Owners.
- Application with signatures of both Owners if House and Adjacent Plot are not owned by same person.
Procedure
- The required documents should be submitted at the Customer Care Services.
- DHA field staff will visit the site.
- A letter will be dispatched along-with specimen of undertaking for use of adjacent plot as lawn to the applicant.
- Undertaking on Rs. 50/- Stamp Paper will be submitted at the Customer Care Services (Building Control Section) by the applicant.
- Approval letter will be sent to the Owner along-with Demarcation Forms to apply for Demarcation of the Plot.
- After physical demarcation the client can construct the boundary wall (around house & plot) and use the plot as lawn.